Vanier Library and Vanier Extension roof and skylight repairs
The project will address water infiltration and support long-term performance.
Project overview
Concordia is carrying out repairs to the roof and skylights of the Vanier Library (VL) Building and the Vanier Extension (VE) to address active water infiltration and protect the building from future leaks.
The work will focus on repairing and replacing select skylights, as well as targeted roof repairs in areas affected by water infiltration. Improvements will also be made to support safe access for future maintenance activities.
Timeline
July to September 2026
Project goals
This project will address active water leaks affecting the VL Building and the VE Extension and improve the long-term performance of the roof and skylights. It will also extend the lifespan of these building components and reduce future maintenance requirements, helping protect the building from future leaks.
Other project goals include:
- Enhancing safety for maintenance personnel
- Improving access for future maintenance activities
What to expect during construction
The VL Building will remain open and accessible throughout the project, with most work taking place on the exterior of the building.
The main entrance to the Georges P. Vanier Library will be temporarily closed during scheduled crane operations. Advance notice will be provided before these activities take place.
Some areas directly beneath the skylights will be temporarily closed for safety reasons while work is underway. The library will remain open, although the interior staircase will be temporarily unavailable during the skylight replacement later in the project. Courses scheduled in affected classrooms will be relocated in advance.
When necessary, service interruptions and work outside the project area will be coordinated with building users to minimize disruptions.