Hall 7 washroom transformation

There are major renovations planned for washrooms in the Henry F. Hall Building. In Fall 2023, work began to transform the men’s and women’s washrooms on the 7th floor into a modern, inclusive space.

Concept drawing by Chevalier Morales Architectes | Paralem Architecture.

Timeline

  • Fall 2023 to Spring 2025
    • Thursday, December 14, 2023: Hall 7 washrooms closed for renovations
    • Week of January 8, 2024: Hall 6 kitchenette and west washroom closed for renovations
    • December 2024: Renovations completed
    • April 2025: Hall 7 washrooms reopened

 

Overview

Facilities Management is committed to improving campus spaces to make them more accessible and inclusive for all.

The new Hall 7 facilities have been designed based on research about universally accessible, gender-inclusive, modern and safe washroom spaces. Designs have also been informed by other Concordia renovations and community feedback about the work.

Goals

  • Create inclusive, safe and universally accessible washrooms.

  • Undertake work in accordance with best practices.

  • Minimize disruptions to the community while work is underway.

  • Meet community needs, respect building code, and optimize space.

Features of new, inclusive washrooms

  • Gender neutral, multi-stall spaces.

  • Individual washrooms options for those who want or need them.

  • Tall stalls for safety and privacy.

  • Bright, open, welcoming space.

A person enters the Hall Building 7th floor inclusive washroom while another person enters an office adjacent to the washrooms. Concept drawing by Chevalier Morales Architectes | Paralem Architecture.

Questions? Ideas? Comments?

Send an email to Facilities Management.