HU building and field behind it: Construction work from March 28 to April 14, 2023
To the users and occupants of the HU Building,
A planned construction project in the HU building and the land behind it is SCHEDULED to take place between Tuesday, 2023-03-28 and Friday, 2023-04-14. This work is necessary to correct the deficiencies of the electrical mass between the Solar House and the HU building.
Buildings
- L- HU / Applied Science Hub
- L- SH / Solar House
General Information
● Two electrical shutdowns for the SH building will take place during the project, the first being on March 29th, the second one is to be confirmed.
● A telecom shutdown will take place in the SH building for the duration of the work.
● Concrete work is expected to take place during the week of April 3rd.
● The work will impact the following:
○ SH building
○ HU SS1 floor
○ HU SS2 floor
● Daily activities of the HU building will not be disturbed.
We thank you for your understanding.
Project Management
Facilities Management