To the users and occupants of the B, D, K, MI and MU annexes,
A planned repair of the exterior of the B, D, K, MI and MU annexes is SCHEDULED to take place from Monday, 2021-11-29, until Tuesday, 2021-11-30 between the hours of 07:30 and 15:30, each day. This work is required to secure some of the exterior masonry that is either cracked, broken, or shifted out of alignment.
Buildings
- B Annex
- D Annex
- K Annex
- MI Annex
- MU Annex
General Information
- The work involves the installation of a wire mesh in various locations around the building.
- A boom lift will be used to carry out the work.
- Daily activities of the building will not be disturbed.
- A flag person will be onsite to assist pedestrians and users of the building will be given access at all times.
- There will be some noise due to some drilling into the exterior wall and the use of a generator.
We thank you for your understanding.
Project Management
Facilities Management