notice
EV Building: Elevators service interruption - January 23, 2026 (07:00 - 16:00)
To the users and occupants of the Hall building,
A planned interruption of the Elevators Bank is SCHEDULED for Friday, 2026-01-23, between the hours 07:00 and 16:00. The Installation of barricades in the elevator hoistway pits is required for New RBQ Code Compliance .
Order of execution:
- North Bank 1 (ENCS tower) – Elevators 1-3 (2 barricades)
- South Bank 2 (ENCS tower) – Elevators 4-6 (2 barricades) –bank with freight
- South East Bank 3 (Fine Arts tower) – Elevators 8-9 (1 barricade)
- S- EV / Engr, Comp. Sci. & Visual Arts Complex
General Information
- One Elevator bank will be Out of Service at a time for approximately 2 hours.
- For access from S2 and S3, while the (ENCS tower –bank with freight) is Out of Service, please use the South East Bank 3 (Fine Arts tower) freight; the call button is on the Frame of the unit.
We thank you for your understanding.
Property Management
Facilities Mangement