notice
UPDATE - Hall Building: Interruption of peripheral heating on Hall 3 - March 5 - 6, 2025 (06:00-16:00)
To the users and occupants of the Hall Building,
A planned interruption of the Peripheral Heating (radiators) is SCHEDULED to occur on Wednesday, 2025-03-05, between the hours of 06:00 and 16:00. If the work cannot be completed on Wednesday it will continue Thursday 2025-03-06 between the hours of 06:00 and 12:00. This shutdown is required to modify the location of the heating pipes and create space for new staircase reinforcements.
Building
General Information
- This work is part of the 21-017 H New Emergency Stair Project.
- Daily building activities will not be impacted.
- The interruption will only impact the offices section on H3.
- Portable heaters will be provided to ensure the offices remain heated during this period.
- This interruption has been coordinated with the office users
We thank you for your understanding,
Project Management