FB Building: Noisy construction work taking place July 19-21 & August 2-3, 2021
To the users and occupants of the FB Building,
As part of the FBSS1 classrooms project, the waterproofing system of the exterior portion of the ramp will be replaced (ramp located on the ground level of the FB tower that leads into the underground parking garage). Demolition activities related to this work are SCHEDULED on the following dates:
- Monday, 2021-07-19 : top slab demolition (using mechanical shovel & hydraulic breaker)
- Tuesday, 2021-07-20 : debris evacuation (using mechanical shovel & bucket)
- Wednesday, 2021-07-21 : drain demolition (using jackhammer)
- Monday, 2021-08-02 : precast concrete panels demolition (using saws)
- Tuesday, 2021-08-03 : precast concrete panels demolition (using saws)
Buildings
- S- FB / Faubourg Building
General Information
- These construction activities are noisy and may be heard in the FB building and outside near the FG and GA buildings.
- If you have the opportunity to do so, you may want to reorganize any noise-sensitive activities during those dates (such as scheduling these in another location or on another day, or working from home).
We thank you for your understanding.