LB Building: Facade inspection from November 30th to December 18th, 2020

November 27, 2020
|
By Amy Caron


To the users and occupants of the LB building,

Please be advised that a planned inspection of the exterior of the LB building is SCHEDULED to take place from Monday, 2020-11-30, until Friday, 2020-12-18, between the hours of 06:30 and 15:00 each day. This is required as part of the LB facade inspection project.  

Buildings

  • S- LB / J.W. McConnell Building

General Information

  • The inspection includes tactile inspection and exploratory openings of all sides of the building (Mackay, Bishop, Maisonneuve, alley).
  • Suspended scaffolding, scissor lifts and nacelles will be used for the inspections.
  • The inspection is weather dependent. No inspection will take place if there is rain, snow or high winds.
  • Daily activities of the building will not be disturbed.
  • The users of the building will be given access at all times.
  • There might be some noisy work due to exploratory openings on the facade.
  • A security perimeter and a guard will be on site to redirect the traffic/pedestrians at the time of equipment set up/dismantling and for the movement of the equipment.
  • Exploratory openings from the inside of the building will be required, and will be coordinated with the affected departments directly.
We thank you for your understanding.