To the users and occupants of the LB Building,
A planned testing of the Elevators #1, #2, #3, #4 is scheduled on Wednesday, 2022-06-29, between the hours of 07:30 and 09:00. These tests are required to verify the control sequence of the elevators in case of a power outage and fire alarm.
Building
S- LB / J.W. McConnell Building
General Information
- Only one elevator will be tested at a time. The other three elevators will remain in service.
- At each test, the elevator being tested will return to the ground floor and stop there.
- A representative of ThyssenKrupp will be at the LB ground floor to inform users of which elevator is being tested and redirect users to the elevators in service.
We thank you for your understanding.
Project Management
Facilities Management